Project Name Location Owner Scope of Services
(PCC, EPC, EPCC etc.)
Description
( of Work Executed)
Provision of Conductor Marine Growth Removal Services for Cendor-A Wellhead Platform. Terengganu, Malaysia Petrofac Malaysia Limited Provision of Conductor Marine Growth Removal Services for Cendor-A Wellhead Platform. Provision of Manpower and ROV Equipment for cleaning and removal of Marine growth on platform jckets at Cendor-A Wellhead Platform.
PL215 (10" TKP-B to TKP-A) Leaks Repair Sarawak, Malaysia Petronas Carigali Sdn Bhd - SKO (As Main Contractor) Supply of Workboat, Deoiling, Subsea Pipeline Leaks Investigation, Leaks Repar and Commissioning Deoiling, Pipeline Leak Investigation and Repair by install of 2 nos Plidco Clamp and Underwater wrapping, Leak Testing and commissioning of PL215 10" TKP-A to TKP-B
Bargeless ROV Pilot Run. Miri Sarawak PETRONAS Carigali Sdn Bhd - SKO (As Main Contractor) Supply Manpower and ROV for Inspection. Underwater Inspection by ROV for Tukau Field.
Pipeline Subsea Repairment & Riser Sect Replacement Sabah, Malaysia PETRONAS Carigali Sdn Bhd - SBO (As Main Contractor) Repair & replace sectional pipeline and riser Repair & replace sectional pipeline and riser of 8" x 4.5km from SMP-A to SMR-A Pipeline
Inspection of Non-Piggable Pipelines. Sarawak, Malaysia Petronas Carigali Sdn Bhd - SKO (As Main Contractor) Supply manpower, equipment and inspection. Non-piggable inpection for 30" x 11km MCOT to SBM pipeline.
PL233 WLP-A to MCOT Pipeline Emergency Leak Repair. Sarawak, Malaysia PETRONAS Carigali Sdn Bhd - SKO (As Main Contractor) Supply of Work Boat, and Emergency Leak Repair. Supply Work Boat for Leak Inspection. De-oiling and Repairfor PL233 WLP-A to MCOT Pipeline.
PL210 (10" TKP-A to WLDP-C) Leak Investigation Sarawak, Malaysia PETRONAS Carigali Sdn Bhd - SKO (As Main Contractor) Supply of Workboat and Subsea Pipeline Leaks Investigation Subsea Pipeline Leaks Investigation by Air Diving Divers for approx 2km for 10" x 17km TKP-A to WLDP-C Pipeline.
PL237 R3 WLP-C Ventline Riser Leak Repair. Sarawak, Malaysia PETRONAS Carigali Sdn Bhd - SKO (As Main Contractor) Supply of Work Boat, Procurement, Construction and Commissioning work of 10" riser sectional replacement. Degassing, Replacement of 10" Riser, Leak Testing and Commissiong the Ventline at WLP-C Platfrom
Provision of Supply of ROV for Pipeline Inspection for Suspected Leak on 12" PuA - TaA Crude Pipeline. Terengganu, Malaysia PETRONAS Carigali Sdn Bhd - PMO Supply of ROV and msnpower for Pipeline Inspection for Suspected Leak on 12" PuA - TaA Crude Pipeline. Supply of ROV and msnpower for Pipeline Inspection for Suspected Leak on 12" PuA - TaA Crude Pipeline.
PL 233 18-Inch WLP-A/MCOT Pipeline De-Commissioning (Deoiling and Riser Removal). Sarawak, Malaysia Petronas Carigali Sdn Bhd - SKO (As Main Contractor) Supply of Work Boat and Riser Removal. Deoiling and Removal of top side piping from Pig Launcher Barrel till splash zone, Riser from Splash zone to seabed and 150 meter subsea pipeline.
PL178 Emergency Repair. Sarawak, Malaysia Petronas Carigali Sdn Bhd - SKO (As Main Contractor) Deoiling, Pipeline Emergency Leak Repair (Plidco Clamp Installation) and Leak Test. Deoiling, Pipeline Leak Investigation and Repair by install of 3 nos Plidco Clamp and Leak Testing of PL178 8" TEP-A to TEP-B
Pre-Grouting Repair Inspection For BAP-A Boat Impact. Sarawak, Malaysia Petronas Carigali Sdn Bhd - SKO (As Main Contractor) Inspection and Repair Pre-Grouting inspection and Engineering Clamp, Fabrication and Installation of Clamps for BAP-A Platfrom's Boat Landing
BAP-A Underwater Inspection. Sarawak, Malaysia PETRONAS Carigali Sdn Bhd - SKO (As Main Contractor) Supply of Accommodation Work Barge and underwater Inspection. Supply Accommodation Work Barge, Jacket Leg inspection, GVI and MPI of all underwater brace members and moduls from splash zone area till seabed.
Installation of Samarang Riser Guard at Sabah Sabah, Malaysia PETRONAS Carigali Sdn Bhd - SKO (As Main Contractor) Work involved data gathering of existing platform Jacket Drawing from PCSB-SBO archived library and then prepare detail engineering design work (sub-contract to others), procurement of structural material, onshore pre-fabrication and offshore installation. Site survey, including diving work. Onshore pre fabrication at Labuan Fabrication yard . Total of 244MT of structural works offshore transportation and installation
Scale Study for Belingan Facilities and Pipelines include Production Chemistry & Scaling Prediction Software. Sarawak, Malaysia PETRONAS Carigali Sdn Bhd - SKO (As Main Contractor) Scale Study and Scale Study Software. Scale Study and Scale Study Software for Belingan Facilities and Pipelines.
Provision of Short Spool Installation for 24" CPP-SCPA Riser at SCPA. Terengganu, Malaysia PETRONAS Carigali Sdn Bhd - PMO Supply manpower and equipment for 24" spool installation. Short Spool installation for 24" CPP-SCPA Riser at SCPA.